Let’s approach this step-by-step:
1) Let’s say the original number of men is x.
2) We can express the relationship between men, days, and work as:
(Number of men) × (Number of days) = (Amount of work)
3) For the original scenario:
x × 6k = Amount of work
4) For the new scenario, let y be the new number of men:
y × 5k = Amount of work
5) Since the amount of work is the same in both cases:
x × 6k = y × 5k
6) We can express y in terms of x:
y = (x × 6k) / 5k = (6/5)x
7) The increase in the number of men is:
y – x = (6/5)x – x = (1/5)x
8) To express this as a percentage:
((1/5)x / x) × 100 = (1/5) × 100 = 20%
Therefore, the number of men should be increased by 20%.